Metering and Reporting Summary

 INCENTIVE
STRUCTURE

 SYSTEM SIZE
MINIMUM

 METER
ACCURACY   
 PMRS
REQUIRED
 PDP
REQUIRED
COST
CAP
 
 EPBI < 30 kW      ± 5%             No No  1% 
 PBI  ≥ 30 kW  ± 2%  Yes  Yes  No Cost Cap

All Host Customers are responsible for the choice and installation of the metering hardware as well as the selection of a Performance Monitoring and Reporting Service (PMRS) provider and/or the Performance Data Provider (PDP). The Host Customer is also responsible for resolving any issues relative to PBI and PMRS performance data.

The list of eligible PMRS providers may be found on the Go Solar CA website: http://www.gosolarcalifornia.org/equipment/monitors+rsp.html

IID's approved Performance Data Providers (PDP) are Power One, DECK Monitoring, Locus Energy and Solectria Renewables. The PDP must submit an application to the IID to be an eligible provider. Please see the PDP Provider Requirements and Application Form.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer